Our website redesign is going badly halfway through. Should we finish it or switch agencies?
Usually neither, yet. Decide once you know what you hold. Check whether you can open the staging site, save a copy of the design files, find every piece of content you've supplied, and log in to the domain, hosting and CMS yourself, then read the contract's deliverables and termination clauses. Some slowdown halfway through is normal friction. Reviews that keep slipping, a staging site that hasn't changed in weeks and an agency that's gone quiet are real trouble. The checks take about 90 minutes.
What it usually means
Halfway is where most redesigns get hard, and the reason is usually dull. What's left is content, migration and a long list of small decisions, and that stretch depends on both sides at once. The agency is waiting on pages, product data and approvals. Your team is waiting on a staging site that looks finished enough to review. Each side reads the other's silence as the problem. In our experience, projects that stall at this point are stuck on words far more often than on design or code.
So the innocent explanation is real, and it's often partly yours. A second reviewer added late, an owner who wants to see every page, content promised for week three that arrived in week nine: any of those can stall a competent agency, and a new one would wait on the same pages. If the contract made writing the copy your job, that split is part of the cause, and handing the copy to whoever finishes the site, old agency or new, is a fix.
The rest belong to the agency, and patience doesn't fix them.
| Cause | What it looks like | What changes it |
|---|---|---|
| Waiting on content or approvalsYou | The agency asks for the same pages or sign-offs more than once | One approver, a date for the content, reviews on the calendar |
| Scope that grewBoth | Pages and features added since the proposal, with no change order | A written list of what's in, what's out and what it moves |
| Past its hoursAgency | Shorter replies, junior people on calls, work done in bursts | A written reset on scope, dates and who's doing the work |
| A key person leftAgency | New names, and decisions you made being asked again | A named lead and a written record of what's decided |
| The agency is in troubleAgency | Staging unchanged for weeks, messages unanswered, dates missed without notice | The checks below, then the decision |
What it costs while it stays this way
The money already spent is gone whichever way you decide, so it shouldn't decide anything. The live question is what each path costs from here. Finishing with a struggling agency costs the rest of the fee plus the risk of launching a site your team isn't happy with, and that has its own price: a site the team quietly dislikes tends to go unedited, and an unedited site drifts out of date until it looks like the one you just paid to replace.
Switching costs more than the new agency's fee. It restarts the parts of a project that live in people's heads. And if you leave before you've secured the files, some of what you paid for may stay behind, because work in progress usually sits in the agency's accounts: its design tool, its staging server, its shared drive.
Every week a stalled project sits, the content you supplied drifts further out of date. The useful window is now, while the agency is still answering, because every check below is harder with a silent vendor, the situation covered in when a web developer stops responding.
- Before noticeSecure the files and logins
Work left in the agency's accounts may stay there.
- HandoverThe new team reads everything
Briefs, discovery notes, designs and the content you've supplied.
- AuditThey test the staging build
Some of it carries over, some gets redone, and they should say which.
- Re-decideYour team approves it again
Decisions made with the old agency get checked again by the new one.
How to confirm it yourself
- Step 1Open the staging site and date the last change
Search your email for staging, preview or dev to find the link, and open it. Compare a few pages with your last review notes and work out roughly when anything last changed. If it sits behind a login only the agency holds, that's your first finding: ask for the staging site password, not the agency's account.
- Step 2Try to save a copy of the design files
If the designs are in Figma and you've been shared on the file, open it, then the main menu, File, then Save local copy. Figma's help says this downloads a .fig file that can be imported into another account, without version history or comments. Viewers can only save a local copy when copying and sharing are enabled on the file, so if the option is missing, the owner has probably restricted it. If you've only ever seen PDFs or screenshots, write that down: the design source is in the agency's hands.
- Step 3Gather every piece of content you've supplied
Search sent mail and shared folders for what your team handed over: page copy, product data, photos, drawings, logos. If it lives in the agency's Google Drive, Google's help says a work account can only transfer file ownership to someone in the same organization, so the agency can't simply hand the files to you. Download them while you still have access. Copy the agency wrote and you approved, if it only exists on staging, goes on the list to request.
- Step 4Log in to the domain, hosting and CMS yourself
Try the registrar, the hosting account, and the CMS for both the live site and the new one. Note which logins work, and in each CMS whether your role is Administrator or something less (in WordPress, if you can open Users, then All Users, the Role column shows it; if the menu only offers Profile, you're not an Administrator). If nobody can name the registrar, run the domain through lookup.icann.org. The full ownership audit is do you actually own your website?; here you only need the list of what you'd have to ask for.
- Step 5Look for an invitation to the code
Search your email for GitHub, GitLab or Bitbucket. If someone at your company was invited to the project's repository, open it, note your role, and download a copy (Code, then Download ZIP). GitHub's documentation says anyone with admin access can transfer a repository to another account, history and issues included, and a personal account has one day to accept. No invitation and no repository usually means the only version you can reach is what staging shows.
- Step 6Read the contract for three clauses
Find the signed proposal or agreement and read for three things: the deliverables and when they're due, how either side can end it (notice period, payment for work done, any termination fee), and when ownership of the work passes to you, often on final payment. If anything is unclear, or the sums are large, check with your lawyer.
- Step 7Put dates on the slippage
From your email, list each review or milestone the agency proposed, the date it was due, the date it happened and who it was waiting on. Be honest in the last column. If most delays were waiting on your team, the first row of the table above is the fix. If most were the agency's, you now have the dated record the conversation needs.
What the agency's answers actually mean
Raise a stalled project and the replies come in familiar forms. What separates friction from trouble is whether the reply comes with a date.
“We're waiting on content from your side.”
Often true, and checkable against the dated list you just made. If it's right, the fix is yours and switching won't help. If the content went over weeks ago, ask what they believe is still missing, page by page.
“It's nearly there. We just need to finish a few things.”
Normal friction when it comes with a list. Trouble when it's the third time you've heard it and staging hasn't changed. Ask what the few things are, who's doing each and when you'll see them on staging.
“Our designer has moved on, but the new person is up to speed.”
People leave agencies, and a good handover inside one is ordinary. The test is whether the new person knows what you decided. If you're being asked about things you settled, ask for the written record of decisions before the next review.
“That's outside the original scope.”
Sometimes fair. It should come as a change order that names the work, the price and the effect on the date. If scope only comes up now, to explain a delay, compare it with the deliverables in the proposal.
“We can't release the files until the project is paid in full.”
Often what the contract says. It rarely covers the content you supplied or accounts in your company's name. Read the ownership clause, and agree what you'd receive for work done to date before you give notice.
What actually fixes it
Match the decision to what the checks found. If most delays were waiting on your side, finish, and fix your side first: one approver, a date for the remaining content, reviews booked. If the agency is the cause but still answering, ask for a reset before anything else: a written list of what's left, who's doing each part and dates you'll see on staging. A reset costs a meeting. If the reply is specific and the next date holds, finishing is usually the cheapest route to a site you're happy with.
Switch when the reset fails, or when the checks show the work isn't really there: staging that hasn't moved, files you can't see, a team that can't say what's decided. Secure the files, the content and the logins first, give the notice the contract asks for, and time the exit to a milestone where the work so far can be paid for and handed over cleanly. Then brief the next agency with everything you collected above. What a B2B website redesign should fix doesn't change with the agency.
A second opinion beats finishing blind when you can't tell whether the work exists. Before paying the next invoice, ask an independent developer or agency to review the staging site, the design file and the deliverables, with read access to the repository or a CMS admin login: staging alone shows how finished the site looks, not how it's built. Whoever reviews it may also want the rebuild, so ask for a page-by-page list of what they'd keep. That costs far less than finishing or restarting blind. Either way, put ownership in writing for the rest of this project or the next: the domain, hosting and accounts in your name and the work assigned to you on payment, the terms the RFP scoring matrix checks a proposal for.
The message to send
To the agency's project lead, before you decide anything. It assumes the delay can be fixed and asks for dates and files, so the reply tells you whether it can. The file request is routine; any agency should be able to send it.
Hi [name],
We'd like to get the redesign back on track. Our last review was on [date], and staging hasn't changed much since. Before our next call, could you send three things by [date one week out]?
A list of what's left, by page and feature, with who's doing each part and the date we'll see it on staging. Anything you're still waiting on from us, so we can get it to you this week. And current copies of the work so far: the design files (a Figma local copy or access to the file), an export of the staging site, read access to the code repository if there is one, and the content we've supplied.
Please also add [company email] as an Administrator on the new site and confirm that the domain and hosting stay in our accounts. If the dates work for both of us, we'll hold the review calendar to them from here.
Common questions
Should we switch web design agencies in the middle of a project?
Only once you know the cause and hold the work. If the delays were mostly waiting on your own content and approvals, a new agency waits on the same things unless it's also taking on the writing. If the agency is the cause, ask for a written reset first. Switch when that fails, after you've secured the files, content and logins and read the contract's termination clause.
Who owns the work if we leave a redesign halfway?
The contract decides. Many agreements pass ownership of the work on final payment, so work in progress may stay with the agency until it's paid for. The content you supplied and accounts in your company's name are yours either way. For code and designs, US law sets the default when the contract is silent: an independent contractor's work isn't automatically work for hire, and without a written assignment the agency owns what it created. Check the clause with your lawyer before you give notice.
How long does a new agency need to pick up a half-finished redesign?
Longer than the work left looks on paper. They have to read the briefs and decisions, test the staging build and decide what carries over before they can quote the rest. Ask any agency you're considering how they take over a project midway and what they'd need from you in the first week.
Do we have to pay the old agency for work we won't use?
Often for work done to date, if the contract says so, since many termination clauses tie a payment to what's been delivered. List what's actually been delivered against the deliverables, and make the handover of those files part of the same payment. If the amounts are significant, check with your lawyer.
Can the half-built site move to our own hosting?
Often, if it's built on a standard CMS. For WordPress, a migration plugin can export the whole staging site as one file another host imports. If it runs on a platform the agency owns, there may be nothing portable to move, which is its own warning sign.